N.C. Gen. Stat. § 62-126.4

Current through Session Law 2024-56
Section 62-126.4 - Commission to establish net metering rates
(a) Each electric public utility shall file for Commission approval revised net metering rates for electric customers that (i) own a renewable energy facility for that person's own primary use or (ii) are customer generator lessees.
(b) The rates shall be nondiscriminatory and established only after an investigation of the costs and benefits of customer-sited generation. The Commission shall establish net metering rates under all tariff designs that ensure that the net metering retail customer pays its full fixed cost of service. Such rates may include fixed monthly energy and demand charges.
(c) Until the rates have been approved by the Commission as required by this section, the rate shall be the applicable net metering rate in place at the time the facility interconnects. Retail customers that own and install an on-site renewable energy facility and interconnect to the grid prior to the date the Commission approves new metering rates may elect to continue net metering under the net metering rate in effect at the time of interconnection until January 1, 2027.

N.C. Gen. Stat. § 62-126.4

Added by 2017 N.C. Sess. Laws 192,s. 6-a, eff. 7/27/2017.