N.C. Gen. Stat. § 62-110.2

Current through Session Law 2024-58
Section 62-110.2 - Electric service areas outside of municipalities
(a) As used in this section, unless the context otherwise requires, the term:
(1) "Premises" means the building, structure, or facility to which electricity is being or is to be furnished; provided, that two or more buildings, structures, or facilities which are located on one tract or contiguous tracts of land and are utilized by one electric consumer for commercial, industrial, institutional, or governmental purposes, shall together constitute one "premises," except that any such building, structure, or facility shall not, together with any other building, structure, or facility, constitute one "premises" if the electric service to it is separately metered and the charges for such service are calculated independently of charges for service to any other building, structure, or facility; and
(2) "Line" means any conductor for the distribution or transmission of electricity, other than
a. In the case of overhead construction, a conductor from the pole nearest the premises of a consumer to such premises, or a conductor from a line tap to such premises, and
b. In the case of underground construction, a conductor from the transformer (or junction point, if there be one) nearest the premises of a consumer to such premises.
(3) "Electric supplier" means any public utility furnishing electric service or any electric membership corporation.
(b) In areas outside of municipalities, electric suppliers shall have rights and be subject to restrictions as follows:
(1) Every electric supplier shall have the right to serve all premises being served by it, or to which any of its facilities for service are attached, on April 20, 1965.
(2) Every electric supplier shall have the right, subject to subdivision (4) of this subsection, to serve all premises initially requiring electric service after April 20, 1965, which are located wholly within 300 feet of such electric supplier's lines as such lines exist on April 20, 1965, except premises which, on said date, are being served by another electric supplier or to which any of another electric supplier's facilities for service are attached.
(3) Every electric supplier shall have the right, subject to subdivision (4) of this subsection, to serve all premises initially requiring electric service after April 20, 1965, which are located wholly within 300 feet of lines that such electric supplier constructs after April 20, 1965, to serve consumers that it has the right to serve, except premises located wholly within a service area assigned to another electric supplier pursuant to subsection (c) hereof.
(4) Any premises initially requiring electric service after April 20, 1965, which are located wholly or partially within 300 feet of the lines of one electric supplier and also wholly or partially within 300 feet of the lines of another electric supplier, as each of such supplier's lines exist on April 20, 1965, or as extended to serve consumers that the supplier has the right to serve, may be served by such one of said electric suppliers which the consumer chooses, and any electric supplier not so chosen by the consumer shall not thereafter furnish service to such premises.
(5) Any premises initially requiring electric service after April 20, 1965, which are not located wholly within 300 feet of the lines of any electric supplier and are not located partially within 300 feet of the lines of two or more electric suppliers may be served by any electric supplier which the consumer chooses, unless such premises are located wholly or partially within an area assigned to an electric supplier pursuant to subsection (c) hereof, and any electric supplier not so chosen by the consumer shall not thereafter furnish service to such premises.
(6) Any premises initially requiring electric service after April 20, 1965, which are located partially within a service area assigned to one electric supplier and partially within a service area assigned to another electric supplier pursuant to subsection (c) hereof, or are located partially within a service area assigned to one electric supplier pursuant to subsection (c) hereof and partially within 300 feet of the lines of another electric supplier, as such lines exist on April 20, 1965, or as extended to serve consumers it has the right to serve, may be served by such one of said electric suppliers which the consumer chooses, and the electric supplier not so chosen shall not thereafter furnish service to such premises.
(7) Any premises initially requiring electric service after April 20, 1965, which are located only partially within a service area assigned to one electric supplier pursuant to subsection (c) hereof and are located wholly outside the service areas assigned to other electric suppliers and are located wholly more than 300 feet from other electric suppliers' lines, may be served by any electric supplier which the consumer chooses, and any electric supplier not so chosen by the consumer shall not thereafter furnish service to such premises.
(8) Every electric supplier shall have the right to serve all premises located wholly within the service area assigned to it pursuant to subsection (c) hereof.
(9) No electric supplier shall furnish temporary electric service for the construction of premises which it would not have the right to serve under this subsection if such premises were already constructed. The construction of lines for, and the furnishing of, temporary service for the construction of premises which any other electric supplier, if chosen by the consumer, would have the right to serve if such premises were already constructed, shall not impair the right of such other electric supplier to furnish service to such premises after the construction thereof, if then chosen by the consumer; nor, unless the consumer chooses to have such premises served by the supplier which furnished the temporary service, shall the furnishing of such temporary service or the construction of a line therefor impair the right of any other electric supplier to furnish service to any other premises which, without regard to the construction of such temporary service line, it has the right to serve.
(10) No electric supplier shall furnish electric service to any premises in this State outside the limits of any incorporated city or town except as permitted by this section; provided, that nothing in this section shall restrict the right of an electric supplier to furnish electric service to itself or to exchange or interchange electric energy with, purchase electric energy from or sell electric energy to any other electric supplier.
(c)
(1) In order to avoid unnecessary duplication of electric facilities, the Commission is authorized and directed to assign, as soon as practicable after January 1, 1966, to electric suppliers all areas, by adequately defined boundaries, that are outside the corporate limits of municipalities and that are more than 300 feet from the lines of all electric suppliers as such lines exist on the dates of the assignments; provided, that the Commission may leave unassigned any area in which the Commission, in its discretion, determines that the existing lines of two or more electric suppliers are in such close proximity that no substantial avoidance of duplication of facilities would be accomplished by assignment of such area. The Commission shall make assignments of areas in accordance with public convenience and necessity, considering, among other things, the location of existing lines and facilities of electric suppliers and the adequacy and dependability of the service of electric suppliers, but not considering rate differentials among electric suppliers.
(2) The Commission, upon agreement of the affected electric suppliers, is authorized to reassign to one electric supplier any area or portion thereof theretofore assigned to another; and the Commission, notwithstanding the lack of such agreement, is authorized to reassign to one electric supplier any area or portion thereof theretofore assigned to another, except premises being served by the other electric supplier or to which any of its facilities for service are attached and except such portions of such area as are within 300 feet of the other electric supplier's lines, upon finding that such reassignment is required by public convenience and necessity. In determining whether public convenience and necessity requires such reassignment, the Commission shall consider, among other things, the adequacy and dependability of the service of the affected electric suppliers, but shall not consider rate differentials between such electric suppliers.
(d) Notwithstanding the provisions of subsections (b) and (c) of this section:
(1) Any electric supplier may furnish electric service to any consumer who desires service from such electric supplier at any premises being served by another electric supplier, or at premises which another electric supplier has the right to serve pursuant to other provisions of this section, upon agreement of the affected electric suppliers; and
(2) The Commission shall have the authority and jurisdiction, after notice to all affected electric suppliers and after hearing, if a hearing is requested by any affected electric supplier or any other interested party, to order any electric supplier which may reasonably do so to furnish electric service to any consumer who desires service from such electric supplier at any premises being served by another electric supplier, or at premises which another electric supplier has the right to serve pursuant to other provisions of this section, and to order such other electric supplier to cease and desist from furnishing electric service to such premises, upon finding that service to such consumer by the electric supplier which is then furnishing service, or which has the right to furnish service, to such premises, is or will be inadequate or undependable, or that the rates, conditions of service or service regulations, applied to such consumer, are unreasonably discriminatory.
(e) The furnishing of electric service in any area which becomes a part of any municipality after April 20, 1965, either by annexation or incorporation, (whether or not such area, or any portion thereof, shall have been assigned pursuant to subsection (c) of this section) shall be subject to the provisions of Part 2, Article 16 of Chapter 160A of the General Statutes, and any provisions of this section inconsistent with said Article shall not be applicable within such area after the effective date of such annexation or incorporation.

N.C. Gen. Stat. § 62-110.2