N.C. Gen. Stat. § 143-134.3

Current through Session Law 2024-53
Section 143-134.3 - No damage for delay clause

No contractual language forbidding or limiting compensable damages for delays caused solely by the owner or its agent may be enforced in any construction contract let by any board or governing body of the State, or of any institution of State government, or of any county, city, town, or other political subdivision thereof. For purposes of this section, the phrase "owner or its agent" does not include prime contractors or their subcontractors.

N.C. Gen. Stat. § 143-134.3

1997-489, s. 1.