Section 4b-91 - (Formerly Sec. 4-137a). Process for bidding for public works contracts. Prequalification requirements. Exceptions
(a)
(1) As used in this section, "prequalification classification" means the prequalification classifications established by the Commissioner of Administrative Services pursuant to section 4a-100, "public agency" has the same meaning as provided in section 1-200, "awarding authority" means the Department of Administrative Services, except "awarding authority" means (A) the Joint Committee on Legislative Management, in the case of a contract for the construction of or work on a building or other public work under the supervision and control of the joint committee, (B) a constituent unit of the state system of higher education, in the case of a contract for the construction of or work on a building or other public work under the supervision and control of such constituent unit, or (C) the Military Department, in the case of a contract for the construction of or work on a building or other public work under the supervision and control of said department and "community court project", "downtown Hartford higher education center project", "correctional facility project", "juvenile residential center project" and "priority higher education facility project" have the same meanings as provided in section 4b-55.
(2) Except as provided in subdivision (3) of this subsection, every contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building or any other public work by the state that is estimated to cost more than one million dollars shall be awarded to the lowest responsible and qualified general bidder who is prequalified pursuant to section 4a-100 on the basis of competitive bids in accordance with the procedures set forth in this chapter, after the awarding authority has invited such bids by posting notice on the State Contracting Portal. The awarding authority shall indicate the prequalification classification required for the contract in such notice.
(3) The requirements set forth in subdivision (2) of this subsection shall not apply to (A) a public highway or bridge project or any other construction project administered by the Department of Transportation, or (B) a contract awarded by the Commissioner of Administrative Services for (i) any public building or other public works project administered by the Department of Administrative Services that is estimated to cost one million five hundred thousand dollars or less, (ii) a community court project, (iii) the downtown Hartford higher education center project, (iv) a correctional facility project, (v) a juvenile residential center project, or (vi) a student residential facility for the Connecticut State University System that is a priority higher education facility project.
(4) Every contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building or any other public work by a public agency that is paid for, in whole or in part, with state funds and that is estimated to cost more than one million dollars shall be awarded to a bidder that is prequalified pursuant to section 4a-100 after the public agency has invited such bids by posting notice on the State Contracting Portal, except for (A) a public highway or bridge project or any other construction project administered by the Department of Transportation, or (B) any public building or other public works project administered by the Department of Administrative Services that is estimated to cost one million five hundred thousand dollars or less. The awarding authority or public agency, as the case may be, shall indicate the prequalification classification required for the contract in such notice.
(5)
(A) The Commissioner of Administrative Services may select contractors to be on lists established for the purpose of providing contractor services for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building or other public works project administered by the Department of Administrative Services involving an expense to the state of one million five hundred thousand dollars or less. The commissioner shall use the prequalification classifications established pursuant to section 4a-100 to determine the specific categories of services that contractors may perform after being selected in accordance with this subparagraph and subparagraph (B) of this subdivision and awarded a contract in accordance with subparagraph (C) of this subdivision. The commissioner may establish a separate list for projects involving an expense to the state of less than one million dollars for the purpose of selecting and utilizing the services of small contractors and minority business enterprises, as such terms are defined in section 4a-60g.
(B) The commissioner shall invite contractors to submit qualifications for each specific category of services sought by the department by posting notice of such invitation on the State Contracting Portal. The notice shall be in the form determined by the commissioner, and shall set forth the information that a contractor is required to submit to be considered for selection. Upon receipt of the submittal from the contractor, the commissioner shall select, for each specified category, those contractors who (i) are determined to be the most responsible and qualified, as such terms are defined in section 4b-92, to perform the work required under the specified category, (ii) have demonstrated the skill, ability and integrity to fulfill contract obligations considering their past performance, financial responsibility and experience with projects of the size, scope and complexity required by the state under the specified category, and (iii) for projects with a cost exceeding one million dollars, have the ability to obtain the requisite bonding. The commissioner shall establish the duration that each list remains in effect, which in no event may exceed three years.
(C) For any public building or public works project involving an expense to the state of one million five hundred thousand dollars or less, the commissioner shall invite bids from only those contractors selected pursuant to subparagraphs (A) and (B) of this subdivision for the specific category of services required for the particular project. The commissioner shall determine the form of bid invitation, the manner of, and time for, submission of bids, and the conditions and requirements of such bids. The contract shall be awarded to the lowest responsible and qualified bidder, subject to the provisions of sections 4b-92 and 4b-94. In the event that fewer than three bids are received in response to an invitation to bid under this subdivision, or that all the bids are in excess of the amount of available funds for the project, the commissioner may negotiate a contract with any of the contractors submitting a bid, or reject the bids received and rebid the project in accordance with this section.
(b) The awarding authority shall determine the manner of submission and the conditions and requirements of such bids, and the time within which the bids shall be submitted, consistent with the provisions of this section and sections 4b-92 to 4b-96, inclusive. Such award shall be made not later than ninety days after the opening of such bids. If the general bidder selected as the general contractor fails to perform the general contractor's agreement to execute a contract in accordance with the terms of the general contractor's general bid and furnish a performance bond and also a labor and materials or payment bond to the amount specified in the general bid form, an award shall be made to the next lowest responsible and qualified general bidder, or, in the case of a contract awarded by the Department of Administrative Services under subdivision (5) of subsection (a) of this section, to the bidder determined in accordance with said subdivision if fewer than three bids are received. No employee of an awarding authority with decision-making authority concerning the award of a contract and no public official, as defined in section 1-79, may communicate with any bidder prior to the award of the contract if the communication results in the bidder receiving information about the contract that is not available to other bidders, except that if the lowest responsible and qualified bidder's price submitted is in excess of funds available to make an award, the awarding authority may negotiate with such bidder and award the contract on the basis of the funds available, without change in the contract specifications, plans and other requirements. If the award of a contract on such basis is refused by such bidder, the awarding authority may negotiate with other contractors who submitted bids in ascending order of bid prices without change in the contract, specifications, plans and other requirements. In the event of negotiation with general bidders as provided in this section, the general bidder involved may negotiate with subcontractors on the same basis, provided such general bidder shall negotiate only with subcontractors named on such general bidder's general bid form.
(c) No person may bid on a contract or perform work pursuant to a contract that is subject to the provisions of subsection (a) of this section unless the person is prequalified in accordance with section 4a-100.
(d) Each bid submitted for a contract described in subsection (c) of this section shall include an update statement in such form as the Commissioner of Administrative Services prescribes and, if required by the public agency soliciting such bid, a copy of the prequalification certificate issued by the Commissioner of Administrative Services. The form for such update statement shall provide space for information regarding all projects completed by the bidder since the date the bidder's prequalification certificate was issued or renewed, all projects the bidder currently has under contract, including the percentage of work on such projects not completed, the names and qualifications of the personnel who will have supervisory responsibility for the performance of the contract, any significant changes in the bidder's financial position or corporate structure since the date the certificate was issued or renewed, any change in the contractor's qualification status as determined by the provisions of subdivision (7) of subsection (c) of section 4a-100 and such other relevant information as the Commissioner of Administrative Services prescribes. Any public agency that accepts a bid submitted without a copy of such prequalification certificate, if required by such public agency soliciting such bid, and an update statement, may become ineligible for the receipt of funds related to such bid, except the public agency soliciting such bids may allow bidders no more than two business days after the opening of bids to submit a copy of the prequalification certificate, if required by such public agency, and an update statement.
(e) Any person who bids on a contract described in subsection (c) of this section shall certify under penalty of false statement at the conclusion of the bidding process that the information in the bid is true, that there has been no substantial change in the bidder's financial position or corporate structure since the bidder's most recent prequalification certificate was issued or renewed, other than those changes noted in the update statement, and that the bid was made without fraud or collusion with any person.
(f) Any person who receives information from a state employee or public official that is not available to the general public concerning any construction, reconstruction, alteration, remodeling, repair or demolition project on a public building or any other public work prior to the date that a notice for bids on the project is posted shall be disqualified from bidding on the project.
(g) Notwithstanding the provisions of this chapter regarding competitive bidding procedures, the commissioner may select and interview at least three responsible and qualified general contractors who are prequalified pursuant to section 4a-100 and submit the three selected contractors to the construction services award panels process described in section 4b-100a and any regulation adopted by the commissioner. The commissioner may negotiate with the successful bidder a contract which is both fair and reasonable to the state for a community court project, the downtown Hartford higher education center project, a correctional facility project, a juvenile residential center project, or a student residential facility for the Connecticut State University System that is a priority higher education facility project. The Commissioner of Administrative Services, prior to entering any such contract or performing any work on such project, shall submit such contract to the State Properties Review Board for review and approval or disapproval by the board, pursuant to subsection (i) of this section. Any general contractor awarded a contract pursuant to this subsection shall be subject to the same requirements concerning the furnishing of bonds as a contractor awarded a contract pursuant to subsection (b) of this section.
(h) Any agency that seeks to have a project awarded without being subject to competitive bidding procedures shall certify to the joint committee of the General Assembly having cognizance of matters relating to government administration and elections that the project is of such an emergency nature that an exception to the competitive bidding procedures of this section is required. Such certification shall include input from all affected agencies, detail the need for the exception and include any relevant documentation.
(i) In the event that the General Assembly approves legislation authorizing an exception to the competitive bidding process for a project, the State Properties Review Board shall complete a review of the contract for such project and approve or disapprove such contract no later than thirty days after the Commissioner of Administrative Services submits such contract to the board. Such review shall be conducted in accordance with the provisions of section 4b-3. In the event that such review does not occur within the thirty-day period prescribed by this subsection, such contract shall be deemed to be approved.
(j) No person whose subcontract exceeds one million dollars in value may perform work as a subcontractor on a project for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building or any other public work by the state or a municipality, except a public highway or bridge project or any other construction project administered by the Department of Transportation, which project is estimated to cost more than one million dollars and is paid for, in whole or in part, with state funds, unless, at the time of the bid submission, the person is prequalified in accordance with section 4a-100. The provisions of this subsection shall not apply to the downtown Hartford higher education center project.
(k) Notwithstanding any provision of this chapter, the Commissioner of Administrative Services may purchase equipment, supplies, materials or other property or services under sections 4a-53 and 4a-66 as required to fulfill his or her responsibilities under this chapter.

Conn. Gen. Stat. § 4b-91

(P.A. 73-528, S. 1, 12; P.A. 74-246, S. 1, 11; P.A. 75-425, S. 23, 57; P.A. 77-614, S. 73, 610; P.A. 82-438, S. 5, 6; 82-447, S. 1; P.A. 84-48, S. 12, 17; P.A. 87-496, S. 41, 110; 87-529, S. 5; P.A. 88-116, S. 4; P.A. 89-353, S. 3, 8; P.A. 92-228 , S. 6 , 9 ; P.A. 93-30 , S. 4 , 14 ; May Sp. Sess. P.A. 94-2 , S. 5 , 203 ; P.A. 95-230 , S. 39 , 45 ; P.A. 96-235 , S. 14 , 19 ; P.A. 97-293 , S. 21 , 26 ; P.A. 98-21 , S. 4 ; 98-59 , S. 2 , 3 ; P.A. 99-26 , S. 4 , 39 ; 99-75 , S. 8 ; 99-241 , S. 50 , 66 ; P.A. 00-192 , S. 17 , 102 ; P.A. 02-140 , S. 3 ; P.A. 03-215 , S. 1 ; P.A. 04-141 , S. 1 ; P.A. 05-287 , S. 10 , 11 ; P.A. 06-134 , S. 18 , 19 , 24 ; P.A. 07-202 , S. 7 ; 07-213 , S. 1 ; Sept. Sp. Sess. P.A. 09-7, S. 161; P.A. 11-51 , S. 90 ; P.A. 13-247 , S. 200 ; P.A. 14-188 , S. 2 , 3 , 8 ; P.A. 16-81 , S. 7 -10; 16-110 , S. 3 .)

Amended by P.A. 23-0204,S. 436 of the Connecticut Acts of the 2023 Regular Session, eff. 10/1/2023.
Amended by P.A. 23-0204,S. 435 of the Connecticut Acts of the 2023 Regular Session, eff. 10/1/2023.
Amended by P.A. 22-0039, S. 5 of the Connecticut Acts of the 2022 Regular Session, eff. 10/1/2022.
Amended by P.A. 21-0104, SS.  4 of the Connecticut Acts of the 2021 Regular Session, 5 of the Connecticut Acts of the 2021 Regular Session eff. 1/1/2022.
Amended by P.A. 21-0198, S. 3 of the Connecticut Acts of the 2021 Regular Session, eff. 7/1/2021.
Amended by P.A. 16-0081, S. 10 of the Connecticut Acts of the 2016 Regular Session, eff. 7/1/2016.
Amended by P.A. 16-0081, S. 9 of the Connecticut Acts of the 2016 Regular Session, eff. 7/1/2016.
Amended by P.A. 16-0081, S. 8 of the Connecticut Acts of the 2016 Regular Session, eff. 7/1/2016.
Amended by P.A. 16-0081, S. 7 of the Connecticut Acts of the 2016 Regular Session, eff. 7/1/2016.
Amended by P.A. 16-0110, S. 3 of the Connecticut Acts of the 2016 Regular Session, eff. 6/3/2016.
Amended by P.A. 14-0188, S. 8 of the Connecticut Acts of the 2014 Regular Session, eff. 7/1/2014.
Amended by P.A. 14-0188, S. 3 of the Connecticut Acts of the 2014 Regular Session, eff. 7/1/2014.
Amended by P.A. 14-0188, S. 2 of the Connecticut Acts of the 2014 Regular Session, eff. 7/1/2014.
Amended by P.A. 09-0007, S. 161 of the Sept. 2009 Sp. Sess., eff. 10/5/2009.

Annotation to former section 4-137a: Cited. 191 C. 497 .