Mass. Gen. Laws ch. 164 § 34B

Current through Chapter 231 of the 2024
Section 164:34B - Removal or installation of poles by distribution company or telephone company

A distribution company or a telephone company engaging in the removal of an existing pole and the installation of a new pole in place thereof shall complete the transfer of wires, all repairs, and the removal of the existing pole from the site within 90 days from the date of installation of the new pole; provided, however, that for any approved commercial or industrial construction project, the completion of which is expected to take longer than one year, said company shall be required to remove such pole within six months from the date of installation of the new pole. The owner of such pole shall notify all other users of the starting date of such removal and installation work at least 48 hours prior to the commencement of such work, and said owner shall require all other users to remove their wiring and other attachments from the poles in a timely manner.

Mass. Gen. Laws ch. 164, § 34B