Va. Code § 58.1-3660

Current with changes from the 2024 legislative session through ch. 845
Section 58.1-3660 - Certified pollution control equipment and facilities
A. Certified pollution control equipment and facilities, as defined herein, are hereby declared to be a separate class of property and shall constitute a classification for local taxation separate from other such classification of real or personal property and such property. Certified pollution control equipment and facilities shall be exempt from state and local taxation pursuant to Article X, § 6 (d) of the Constitution of Virginia.
B. As used in this section:

"Certified pollution control equipment and facilities" means any property, including real or personal property, equipment, facilities, or devices, used primarily for the purpose of abating or preventing pollution of the atmosphere or waters of the Commonwealth and which the state certifying authority or subdivision certifying authority having jurisdiction with respect to such property has certified to the Department of Taxation as having been constructed, reconstructed, erected, or acquired in conformity with the state program or requirements for abatement or control of water or atmospheric pollution or contamination, except that in the case of equipment, facilities, devices, or other property intended for use by any political subdivision in conjunction with the operation of its water, wastewater, stormwater, or solid waste management facilities or systems, including property that may be financed pursuant to Chapter 22 (§ 62.1-224 et seq.) of Title 62.1, the state certifying authority or subdivision certifying authority having jurisdiction with respect to such property shall, upon the request of the political subdivision, make such certification prospectively for property to be constructed, reconstructed, erected, or acquired for such purposes. Such property shall include, but is not limited to, any equipment used to grind, chip, or mulch trees, tree stumps, underbrush, and other vegetative cover for reuse as mulch, compost, landfill gas, synthetic or natural gas recovered from waste or other fuel, and equipment used in collecting, processing, and distributing, or generating electricity from, landfill gas or synthetic or natural gas recovered from waste, whether or not such property has been certified to the Department of Taxation by a state certifying authority or subdivision certifying authority. Such property shall include solar energy equipment, facilities, or devices owned or operated by a business that collect, generate, transfer, or store thermal or electric energy whether or not such property has been certified to the Department of Taxation by a state certifying authority or subdivision certifying authority. Such property shall also include energy storage systems, whether or not such property has been certified to the Department of Taxation by a state certifying authority or subdivision certifying authority. All such property as described in this definition shall not include the land on which such equipment or facilities are located.

"Energy storage system" means equipment, facilities, or devices that are capable of absorbing energy, storing it for a period of time, and redelivering that energy after it has been stored.

"State certifying authority" means the State Water Control Board or the Virginia Department of Health, for water pollution; the State Air Pollution Control Board, for air pollution; the Department of Energy, for solar energy projects, energy storage systems, and for coal, oil, and gas production, including gas, natural gas, and coalbed methane gas; and the Virginia Waste Management Board, for waste disposal facilities, natural gas recovered from waste facilities, and landfill gas production facilities, and shall include any interstate agency authorized to act in place of a certifying authority of the Commonwealth.

Subdivision certifying authority" means the body of a political subdivision responsible for administering the political subdivision's water, wastewater, stormwater, or solid waste management facilities or systems. A subdivision certifying authority may only certify property pursuant to this section if the property being certified is equipment, facilities, devices, or other property intended for use by the political subdivision in conjunction with the operation of its water, wastewater, stormwater, or solid waste management facilities or systems. If property is certified by a subdivision certifying authority, it shall not be required to be certified by a state certifying authority.

C. For solar photovoltaic (electric energy) systems, this exemption applies only to (i) projects equaling 20 megawatts or less, as measured in alternating current (AC) generation capacity, for which an initial interconnection request form has been filed with an electric utility or a regional transmission organization on or before December 31, 2018; (ii) projects equaling 20 megawatts or less, as measured in alternating current (AC) generation capacity, that serve any of the public institutions of higher education listed in § 23.1-100 or any private college as defined in § 23.1-105; (iii) 80 percent of the assessed value of projects for which an initial interconnection request form has been filed with an electric utility or a regional transmission organization (a) between January 1, 2015, and June 30, 2018, for projects greater than 20 megawatts or (b) on or after July 1, 2018, for projects greater than 20 megawatts and less than 150 megawatts, as measured in alternating current (AC) generation capacity, and that are first in service on or after January 1, 2017; (iv) projects equaling five megawatts or less, as measured in alternating current (AC) generation capacity, for which an initial interconnection request form has been filed with an electric utility or a regional transmission organization on or after January 1, 2019; and (v) 80 percent of the assessed value of all other projects equaling more than five megawatts and less than 150 megawatts, as measured in alternating current (AC) generation capacity for which an initial interconnection request form has been filed with an electric utility or a regional transmission organization on or after January 1, 2019.
D. The exemption for solar photovoltaic (electric energy) projects greater than five megawatts, as measured in alternating current (AC) generation capacity, shall not apply to any such project unless an application has been filed with the locality for the project before July 1, 2030, regardless of whether a locality assesses a revenue share on such project pursuant to the provisions of § 58.1-2636. If a locality adopts an energy revenue share ordinance under § 58.1-2636, the exemption for solar photovoltaic (electric energy) projects greater than five megawatts, as measured in alternating current (AC) generation capacity, shall be 100 percent of the assessed value. If a locality does not adopt an energy revenue share ordinance under § 58.1-2636, the exemption for solar photovoltaic (electric energy) projects greater than five megawatts, as measured in alternating current (AC) generation capacity, for which an initial interconnection request form has been filed with an electric utility or a regional transmission organization, shall be 80 percent of the assessed value when an application has been filed with the locality prior to July 1, 2030. For purposes of this subsection, "application has been filed with the locality" means an applicant has filed an application for a zoning confirmation from the locality for a by-right use or an application for land use approval under the locality's zoning ordinance to include an application for a conditional use permit, special use permit, special exception, or other application as set out in the locality's zoning ordinance.
E. For pollution control equipment and facilities certified by the Virginia Department of Health, this exemption applies only to onsite sewage systems that serve 10 or more households, use nitrogen-reducing processes and technology, and are constructed, wholly or partially, with public funds.
F. Notwithstanding any provision to the contrary, for any solar photovoltaic project described in clauses (iii) and (v) of subsection C for which an initial interconnection request form has been filed with an electric utility or a regional transmission organization on or after January 1, 2019, the amount of the exemption shall be as follows: 80 percent of the assessed value in the first five years in service after commencement of commercial operation, 70 percent of the assessed value in the second five years in service, and 60 percent of the assessed value for all remaining years in service.
G. Notwithstanding any provision to the contrary, the exemption for energy storage systems provided under this section (i) shall apply only to projects greater than five megawatts and less than 150 megawatts, as measured in alternating current (AC) storage capacity, and (ii) shall be in the following amounts: 80 percent of the assessed value in the first five years of service after commencement of commercial operation, 70 percent of the assessed value in the second five years in service, and 60 percent of the assessed value for all remaining years in service.
H. The exemption for energy storage systems greater than five megawatts, as measured in alternating current (AC) storage capacity, shall not apply to any such project unless an application has been filed with the locality for the project before July 1, 2030, regardless of whether a locality assesses a revenue share on such project pursuant to the provisions of § 58.1-2636. If a locality adopts an energy revenue share ordinance under § 58.1-2636, the exemption for energy storage systems greater than five megawatts, as measured in alternating current (AC) storage capacity, shall be 100 percent of the assessed value. If a locality does not adopt an energy revenue share ordinance under § 58.1-2636, the exemption for energy storage systems greater than five megawatts, as measured in alternating current (AC) storage capacity, shall be as set out in subsection G when an application has been filed with the locality prior to July 1, 2030. For the purposes of this subsection, "application has been filed with the locality" means an applicant has filed an application for a zoning confirmation from the locality for a by-right use or an application for land use approval under the locality's zoning ordinance to include an application for a conditional use permit, special use permit, special exception, or other application as set out in the locality's zoning ordinance.

Va. Code § 58.1-3660

Code 1950, § 58-16.3; 1972, c. 694; 1984, c. 675; 1995, c. 229; 2003, c. 859; 2006, cc. 375, 939; 2009, c. 671; 2014, cc. 259, 737; 2016, cc. 346, 518; 2018, c. 849; 2019, c. 441; 2020, cc. 65, 252, 1028, 1029, 1224, 1270; 2021, Sp. Sess. I, cc. 49, 50, 532; 2022, cc. 14, 501.
Amended by Acts 2022 c. 501,§ 1, eff. 7/1/2022.
Amended by Acts 2022 c. 14,§ 1, eff. 7/1/2022.
Amended by Acts 2021SP1 c. 532,§ 1, eff. 10/1/2021.
Amended by Acts 2020 c. 1270,§ 1, eff. 7/1/2020.
Amended by Acts 2020 c. 1224,§ 1, eff. 7/1/2020.
Amended by Acts 2020 c. 1028, § 1, eff. 7/1/2020.
Amended by Acts 2020 c. 1029, § 1, eff. 7/1/2020.
Amended by Acts 2020 c. 252, § 1, eff. 7/1/2020.
Amended by Acts 2020 c. 65, § 1, eff. 7/1/2020.
Amended by Acts 2019 c. 441, § 1, eff. 3/18/2019.
Amended by Acts 2018 c. 849, § 1, eff. 7/1/2018.
Amended by Acts 2016 c. 518, § 1, eff. 7/1/2016.
Amended by Acts 2016 c. 346, § 1, eff. 1/1/2017.
Amended by Acts 2014 c. 737, § 1, eff. 1/1/2015.
Amended by Acts 2014 c. 259, § 1, eff. 1/1/2015.