The Commission shall approve such underground construction within 30 days of receipt of the written request of the public utility to participate in the pilot program pursuant to this section. The Commission shall not require the submission of additional technical and cost analyses as a condition of its approval but may request such analyses for its review. The Commission shall approve the underground construction of one contiguous segment of the transmission line that is approximately 3.1 miles in length that was previously proposed for construction within or immediately adjacent to the right-of-way of the interstate highway, for which, by resolution, the locality has indicated general community support. The remainder of the construction for the transmission line shall be aboveground. The Commission shall not be required to perform any further analysis as to the impacts of this route, including environmental impacts or impacts upon historical resources.
The electric utility may proceed to acquire right-of-way and take such other actions as it deems appropriate in furtherance of the construction of the approved transmission line, including acquiring the cables necessary for the underground installation.
Va. Code § 56-585.1:5