The requirements of this subsection for hobby boilers only testing to one and one-half times the maximum allowable working pressure or full radiographic or ultrasonic examination may be waived after the initial inspection if the inspector finds that the general standards of subsection B are met and the safety valve or valves are set at the maximum allowable working pressure determined by the following: calculations from the ultrasonic results or 100 pounds per square inch, whichever is lower. If a variance is requested for butt strap hobby boilers, the Commissioner shall not deny such variance request without a given, valid reason.
The requirements of this subsection for model boilers only for testing to twice the maximum allowable working pressure or full radiographic or ultrasonic examination may be waived after the initial inspection if the inspector finds that the general standards of subsection B are met and the safety valve or valves are set at the maximum allowable working pressure determined by the following: calculations from the ultrasonic results or 100 pounds per square inch, whichever is lower.
Any boiler which has been without a documented inspection within the past twenty years must have a two times maximum allowable working pressure hydro test prior to its operation.
Va. Code § 40.1-51.19:3