Section 7-714 - Prevailing worker wage rate

The developer of a solar energy generating system that has a generating capacity over 1 megawatt, as measured by the alternating current rating of the system's inverter, shall ensure that workers are paid not less than the prevailing wage rate determined under Title 17, Subtitle 2 of the State Finance and Procurement Article.

Md. Code art. Public Utilities, § 7-714Md. Code, Public Utilities § 7-714

Added by 2024 Md. Laws, Ch. 595,Sec. 1, eff. 6/1/2024.