Section 22185 - [Effective Until 1/1/2030] Definitions For purposes of this chapter, the following definitions apply:
(a)(1) "Best value" means a value determined by evaluation of objective criteria that may include, but are not limited to, price, features, function, life-cycle costs, experience, and past performance.(2) A best value determination may involve the selection of the lowest cost proposal meeting the interests of the local agency and the objectives of the project.(b) "Construction subcontract" means each subcontract awarded by the design-build entity to a subcontractor that will perform work or labor or render service to the design-build entity in or about the construction of the work or improvement, or a subcontractor licensed by the State of California that, under subcontract to the design-build entity, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications produced by the design-build team.(c) "Design-build entity" means a corporation, limited liability company, partnership, joint venture, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services as needed pursuant to a design-build contract.(d) "Design-build project" means any project using the progressive design-build construction procurement process described in this chapter, but does not include projects on state-owned or state-operated facilities.(e) "Design-build team" means the design-build entity itself and the individuals and other entities identified by the design-build entity as members of its team. Members shall include the general contractor and, if utilized in the design of the project, all electrical, mechanical, and plumbing contractors.(f) "Guaranteed maximum price" means the maximum payment amount agreed upon by the local agency and the design-build entity for the design-build entity to finish all remaining design, preconstruction, and construction activities sufficient to complete and close out the project.(g) "Local agency" means a city, county, city and county, or special district.(h) "Progressive design-build" means a project delivery process in which both the design and construction of a project are procured from a single entity that is selected through a qualifications-based selection at the earliest feasible stage of the project.(i) "Qualifications-based selection" means the process by which the local agency solicits for services from the design-build entities and that price is not the sole factor as the basis of award.Ca. Pub. Cont. Code § 22185
Added by Stats 2023 ch 500 (SB 706),s 1, eff. 1/1/2024.