Cal. Pub. Contract Code § 22172.4

Current through the 2023 Legislative Session.
Section 22172.4 - [Effective until 1/1/2029] Retention proceeds
(a)If the local agency elects to award a project pursuant to this chapter, retention proceeds withheld by the local agency from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation. Work performed to establish the guaranteed maximum price shall not be subject to retention.
(b)In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the local agency and the design-build entity. If the design-build entity provides written notice to any subcontractor that is not a member of the design-build entity, before or at the time the bid is requested, that a bond may be required, and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the local agency and the design-build entity from any payment made by the design-build entity to the subcontractor.

Ca. Pub. Cont. Code § 22172.4

Added by Stats 2022 ch 243 (SB 991),s 1, eff. 1/1/2023.