Current through the 2023 Legislative Session.
Section 20663.4 - [Effective until 1/1/2025] Selection of contractorSelection of the best value contractor shall be made as follows:
(a)(1) The community college district shall evaluate the qualifications of the bidders based solely upon the criteria set forth in the solicitation documents, and shall assign a qualification score to each bid.(2) Qualification scores shall be determined by using only the criteria and selection procedures specifically identified in the request for proposals. The following minimum factors, however, shall be weighted as deemed appropriate by the community college district:(C) Other factors identified in the request for proposal.(b) To determine the best value contractor, the community college district shall divide each bidder's price by its qualifications score. A preference of up to 5 percent shall be applied to the price of a bid submitted by a small business, as defined by the community college district, before dividing the bidder's price by its qualification score. The lowest resulting cost per quality point will represent the best value bid. The award of the contract shall be made to the bidder whose bid is determined, by the community college district in writing, to be the best value to the community college district.(c) The community college district shall issue a written decision of its contract award or else reject all bids.(d) Upon issuance of a contract award, the community college district shall publicly announce its award identifying the project, the project price, the best value contractor to which the award is made, as well as the prices, qualification scores, and resulting costs per qualification point for all responsive bidders. The contract file shall include documentation sufficient to support the decision to award.Ca. Pub. Cont. Code § 20663.4
Added by Stats 2019 ch 173 (AB 356),s 1, eff. 1/1/2020.