Current through the 2023 Legislative Session.
Section 10198.6 - Retention proceeds withheld by the department from the design-build entity(a) If the department elects to award a project pursuant to this article, retention proceeds withheld by the department from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation. Work performed to establish the guaranteed maximum price shall not be subject to retention.(b) In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the department and the design-build entity. If the design-build entity provides written notice to any subcontractor that is not a member of the design-build entity, before or at the time the bid is requested, that a bond may be required, and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the department and the design-build entity from any payment made by the design-build entity to the subcontractor.Ca. Pub. Cont. Code § 10198.6
Added by Stats 2021 ch 77 (AB 137),s 26, eff. 7/16/2021.