Cal. Pub. Contract Code § 10112.3

Current through the 2024 Legislative Session.
Section 10112.3 - [Effective until 1/1/2033] Progression of Construction Manager/General Contractor method

Construction Manager/General Contractor method projects shall progress as follows:

(a)
(1) The department shall establish a procedure for the evaluation and selection of a construction manager through a request for qualifications (RFQ). The RFQ shall include, but not be limited to, the following:
(A) If the construction manager is a partnership, limited partnership, or other association, a list of all of the partners, general partners, or association members known at the time of the statement of qualifications submission who will participate in the Construction Manager/General Contractor method contract.
(B) Evidence that the members of the construction manager have completed, or demonstrated the experience, competency, capability, and capacity to complete projects of similar size, scope, or complexity, and that proposed key personnel have sufficient experience and training to competently manage and complete the construction of the project, as well as a financial statement that assures the department that the construction manager has the capacity to complete the project, construction expertise, and an acceptable safety record.
(C) The licenses, registration, and credentials required to construct the project, including information on the revocation or suspension of any license, registration, or credential.
(D) Evidence that establishes that the construction manager has the capacity to obtain all required payment and performance bonding, liability insurance, and errors and omissions insurance.
(E) Any prior serious or willful violation of the California Occupational Safety and Health Act of 1973 (Part 1 (commencing with Section 6300) of Division 5 of the Labor Code), or the federal Occupational Safety and Health Act of 1970 (Public Law 91-596), settled against any member of the construction manager, and information concerning workers' compensation experience history and worker safety program.
(F) Information concerning any debarment, disqualification, or removal from a federal, state, or local government public works project. Any instance in which a construction manager, its owners, officers, or managing employees submitted a bid on a public works project and were found to be nonresponsive or were found by an awarding body not to be a responsible bidder.
(G) Any instance in which the construction manager, or its owners, officers, or managing employees, defaulted on a construction contract.
(H) Any violations of the Contractors' State License Law (Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code), excluding alleged violations of federal or state law including the payment of wages, benefits, apprenticeship requirements, or personal income tax withholding, or of the Federal Insurance Contributions Act (26 U.S.C. Sec. 3101, et seq.) withholding requirements settled against any member of the construction manager.
(I) Information concerning the bankruptcy or receivership of any member of the construction manager, including information concerning any work completed by a surety.
(J) Information concerning all settled adverse claims, disputes, or lawsuits between the owner of a public works project and any member of the construction manager during the five years preceding submission of a bid pursuant to this section, in which the claim, settlement, or judgment exceeds fifty thousand dollars ($50,000). Information shall also be provided concerning any work completed by a surety during this period.
(K) In the case of a partnership or other association that is not a legal entity, a copy of the agreement creating the partnership or association and specifying that all partners or association members agree to be fully liable for the performance under the contract.
(L) For the purposes of this paragraph, a construction manager's safety record shall be deemed acceptable if their experience modification rate for the most recent three-year period is an average of 1.00 or less, and their average total recordable injury/illness rate and average lost work rate for the most recent three-year period does not exceed the applicable statistical standards for its business category.
(2) The information required pursuant to this subdivision shall be verified under oath by the construction manager and its members in the manner in which civil pleadings in civil actions are verified. Information that is not a public record pursuant to the California Public Records Act (Division 10 (commencing with Section 7920.000) of Title 1 of the Government Code) shall not be open to public inspection.
(b) For each RFQ, the department shall generate a final list of qualified persons or firms that participated in the RFQ prior to entering into negotiations on the contract or contracts to which the RFQ applies.
(c)
(1) For each contract included in the RFQ, the department shall enter into separate negotiations for the contract with the highest qualified person or firm on the final list for that contract. However, if the RFQ is for multiple contracts and specifies that all of the multiple contracts will be awarded to a single construction manager, there may be a single negotiation for all of the multiple contracts. The negotiations shall include consideration of compensation and other contract terms that the department determines to be fair and reasonable to the department. In making this decision, the department shall take into account the estimated value, the scope, the complexity, and the nature of the professional services or construction services to be rendered. If the department is not able to negotiate a satisfactory contract with the highest qualified person or firm on the final list, regarding compensation and on other contract terms the department determines to be fair and reasonable, the department shall formally terminate negotiations with that person or firm. The department may undertake negotiations with the next most qualified person or firm on the final list in sequence until an agreement is reached, or a determination is made to reject all persons or firms on the final list.
(2) If a contract for construction services is entered into pursuant to this article and includes preconstruction services by the construction manager, the department shall enter into a written contract with the construction manager for preconstruction services under which contract the department shall pay the construction manager a fee for preconstruction services in an amount agreed upon by the department and the construction manager. The preconstruction services contract may include fees for services to be performed during the contract period provided, however, the department shall not request or obtain a fixed price or a guaranteed maximum price for the construction contract from the construction manager or enter into a construction contract with the construction manager until after the department has entered into a preconstruction services contract that shall provide for the subsequent negotiation for construction of all or any discreet phase or phases of the project.
(3) A contract for construction services shall be awarded after the plans have been sufficiently developed and either a fixed price or a guaranteed maximum price has been successfully negotiated. If a fixed price or a guaranteed maximum price is not negotiated, the department shall not award the contract for construction services.
(4) The department is not required to award the construction services contract.
(5) Construction shall not commence on any phase, package, or element until the department and construction manager agree in writing on either a fixed price that the department will pay for the construction to be commenced or a guaranteed maximum price for the construction to be commenced and construction schedule for the project. The construction manager shall perform not less than 30 percent of the work covered by the fixed price or guaranteed maximum price agreement reached. Work that is not performed directly by the construction manager shall be bid to subcontractors pursuant to Section 10112.5.

Ca. Pub. Cont. Code § 10112.3

Amended by Stats 2022 ch 28 (SB 1380),s 129, eff. 1/1/2023.
Added by Stats 2021 ch 247 (SB 626),s 1, eff. 1/1/2022.