Current with legislation from 2024 Fiscal and Special Sessions.
Section 8-9-807 - Construction and operationThe entities under the federal charter under § 8-9-804 shall be responsible for the construction and operation of the spent nuclear fuel interim storage and recycling facility and through the use of federal funds shall:
(1) Receive the design documentation completed under § 8-9-804;(2) Develop construction documents, update cost data, and establish a schedule for construction to be completed with a national laboratory;(3) Contract with a design firm to provide design and construction documents for the spent nuclear fuel interim storage and recycling facility containment building;(4) Contract with a contractor to build the spent nuclear fuel interim storage and recycling facility as designed and provide start-up assistance with the spent nuclear fuel interim storage and recycling facilities; and(5) Contract with a national laboratory to provide installation management of the pyrotechnic lines inside the spent nuclear fuel interim storage and recycling facility containment building and to provide start-up management and training for permanent operators and maintenance.Added by Act 2023, No. 259,§ 1, eff. 8/1/2023.