Ariz. Rev. Stat. § 33-904

Current through L. 2024, ch. 259
Section 33-904 - Duration of lien

A lien provided for in this article is not impressed upon a crop for a longer period than six calendar months after the claim is filed, unless a civil action is commenced within that time to foreclose the lien.

A.R.S. § 33-904