PURSUANT TO UTCR 13.160(2)
Pursuant to UTCR 13.160(2), except for good cause shown, the hearing must be scheduled to take place not later than 91 days, measured from the date of assignment to arbitration. With the exception of applying this 91-day time period in place of the 49-day time period set in UTCR 13.160(3), all other requirements of UTCR 13.160(3) and (4) apply to the scheduling, postponement or continuance of an arbitration hearing.
Josephine Supp. L. R. 13.121