085-1 Wyo. Code R. § 1-16

Current through April 27, 2019
Section 1-16 - Fund Disbursement, Project Monitoring, Performance Measures and Revenue Recapture Reporting

(a) Procurement Standards. Applicants must follow state procurement regulations for cities and towns and the Wyoming Preference Act. If a non-municipal applicant has a procurement policy, staff or qualified consultants reserve the right to review that policy prior to fund disbursements.

(b) Fund Disbursement. Funds shall be disbursed to the applicant only as needed to discharge obligations incurred in accordance with the Board approved eligible project costs. Request for disbursement shall be made via the online grant management system, access to which shall be provided by Council staff. Requests for fund disbursement must be supported by adequate proof that such an obligation has been incurred for the project purpose and is due and owing.

(c) Fund Reversion.

  • (i) If the Council staff determines that a project has not been completed within a reasonable time, Council staff shall notify the applicant in writing at least thirty (30) days prior to presenting the matter for Council review.
  • (ii) If the Council staff determines that the project is complete, but the full amount of the grant or loan has not been expended, the Council staff shall notify grantee of this determination. Thirty (30) days following the notification, the unused portion of the grant or loan shall revert to the BRC Fund.
  • (iii) For projects that have not been started within one year: Council staff will notify a grantee/borrower of a pending expiration prior to the one-year anniversary of the grant/loan approval. The grantee/borrower can submit a written request to continue the project. Council staff may request new and/or updated information and documentation. Council staff may recommend and the Council may grant an extension of time in which to start the project or terminate the project.
  • (iv) For projects with contingencies: Council staff may request a monthly update on the status of the contingencies. The grantee/borrower has the option to submit a new application or may request an extension or modification of the contingency terms through the Council staff. Council staff may recommend and the Council may grant an extension of time or modification to the contingencies.

(d) Project Monitoring.

  • (i) Reports. Within fifteen (15) calendar days of the conclusion of each calendar quarter during the term of the grant or loan contract, the applicant shall supply Council staff with a progress report. Each progress report shall set forth in narrative form the work accomplished under the grant or loan during the quarter and shall include a financial status report. At the end of the project, the applicant shall furnish Council staff with a comprehensive report of the project. The applicant shall likewise furnish the Council staff with a cumulative financial statement, reflecting the total expenditure pursuant to this grant agreement.
  • (ii) Audits and inspections. The Council staff may, at its expense, conduct an audit of the records of the applicant and inspect the construction and operation of the project.
  • (iii) Record retention. Grantee agrees to retain all records related to the project for five (5) years following the Council staff's date of notice to grantee of closeout of the grant.

(e) Project Evaluation.

  • (i) Reports. Upon project construction, the grantee/borrower shall annual reports for five years project outcomes against established measures. Council staff shall tailor reports to the specific nature of each grant or loan, in agreements between the Council and grantee.
  • (ii) Evaluation results. The Council shall use the evaluation report information to measure program outcomes, to promote learning from experience and to improve program performance. Evaluation results will be available to other grantees.
  • (iii) At the end of the term of a BRC project, the Grantee/Borrower shall provide a comprehensive report to the Council staff, in a format prescribed by the Council staff that is a cumulative financial and performance report of the project. This report shall, at a minimum, include a detailed accounting of project expenditures that were paid for with BRC grant or loan funds, match contributed, recapture revenue(s) received, how recaptured revenues were or will be used, how recaptured revenue use complies with the rules of the BRC program and the project grant/loan agreement and a list of the accomplishments that resulted from the grant or loan. An authorized official of the Grantee/Borrower shall certify, under penalty of false swearing, that the information in the report is true. The Council staff reserves the right to require a BRC project audit to be conducted by the director of the department of audit or his designee. The cost of this audit shall be the responsibility of the Grantee/Borrower.
  • (iv) A grant/loan recipient shall keep recapture funds in a segregated account and report on such to council staff for the term of the revenue recapture agreement.

085-1 Wyo. Code R. § 1-16

Adopted, Eff. 7/25/2016.