(a) The Council may adopt a funding allocation plan for BRC projects and prioritize project types.
(b) Applications will be accepted according to an annual deadline schedule posted by the Council.
(c) BRC awards per applicant are limited as follows:
Business Committed | No Limit |
Managed Data Center Cost Reduction | No Limit |
Community Readiness | One per calendar year |
Community Enhancement | One per calendar year |
Planning | One per calendar year |
(d) An applicant may request, with a single application, grant or loan funds up to the annual maximum amount for a multi-year project for a period not to exceed three (3) fiscal years. The applicant must demonstrate how the project meets the definition of a multi-year project.
085-1 Wyo. Code R. § 1-13
Amended, Eff. 7/25/2016.