(a) An Owner/Operator of a well or wells shall notify the Supervisor of all above and below ground flowlines and vessels, including tanks, if the flowlines or vessels are not used for a period of two (2) years. After consideration of the relevant circumstances, the Supervisor on a case-by-case basis, may require the flowline or facilities to be purged with fresh water or inert gases, drained and depressured. The Owner/Operator shall provide notification of the purging operation to the Supervisor or Authorized Agent.
(b) The Supervisor may require the Owner or Operator to abandon and/or remove all above ground piping. If flowlines or facility piping are removed, the removal shall be done in a manner that prevents the escape of fluids, that is:
(c) If underground flowlines or facility piping are abandoned in place, the Owner or Operator shall meet the following requirements:
055-4 Wyo. Code R. § 4-15
Amended, Eff. 6/3/2015.