053-3 Wyo. Code R. § 57.6407

Current through April 27, 2019
Section 57.6407 - Circuit testing

A blasting galvanometer or other instrument designed for testing blasting circuits shall be used to test the following:

(a) In surface operations-

  • (1) Continuity of each electric detonator in the blasthole prior to stemming and connection to the blasting line;
  • (2) Resistance of individual series or the resistance of multiple balanced series to be connected in parallel prior to their connection to the blasting line;
  • (3) Continuity of blasting lines prior to the connection of electric detonator series; and
  • (4) Total blasting circuit resistance prior to connection to the power source.

(b) In underground operations-

  • (1) Continuity of each electric detonator series; and
  • (2) Continuity of blasting lines prior to the connection of electric detonators.

    NONELECTRIC BLASTING-SURFACE AND UNDERGROUND

053-3 Wyo. Code R. § 57.6407