a . The general requirements for application and registration forms (see Section 3 of this Chapter) also apply to "Statement of Completion and Description of Well" forms (Form U.W. 6 and U.W. 7) and "Proof of Appropriation and Beneficial Use of Ground Water" (Form U.W. 8). All forms will be examined by the State Engineer's Office, and if found to be acceptable, will be considered for approval. If a "Statement of Completion and Description of Well" form or a "Proof of Appropriation and Beneficial Use of Ground Water" form is not complete, or it is defective in some way, the permittee will be requested to provide the information necessary to place the document in proper order. If necessary, the form will be returned to the permittee by certified mail for correction. The reasons for such return and the time allowed to make the necessary corrections (usually 90 days) shall be stated by letter accompanying the form. If the form is not returned to the State Engineer within the specified time period, or if the permittee fails to furnish the requested written information, the permit may be cancelled. The permittee may request additional time to make such corrections, explaining why such an extension is required. A written request for an extension of time must be received in the State Engineer's Office before the expiration of the time period.
b. If Part I of a "Proof of Appropriation and Beneficial Use of Ground Water" form (Form U.W. 8) is received in acceptable condition, but without Part II, the required map, a period of 6 months will be allowed to submit the map. The information submitted on Form U.W. 8 and the map will be used as a basis for the adjudication of the ground water right.
037-2 Wyo. Code R. § 2-11