Section 14-5 - Determination of Delivery Method

(a) Projects shall be designed and constructed using the design-bid-build delivery method unless extenuating circumstances exist that necessitate the adoption of an alternate method. District requests for the Commission to approve an alternate design and construction delivery method shall explain the reason(s) an alternate project delivery method is preferable to the design-bid-build delivery method.

(b) The Commission shall consider the following non-exclusive and non-prioritized list of factors in making a determination to allow alternate design and construction delivery methods:

  • (i) Size and complexity of the remedy;
  • (ii) Budget and availability of funds;
  • (iii) Urgency of time;
  • (iv) Past experience with the delivery method;
  • (v) Anticipated cost of the possible various delivery methods;
  • (vi) Market conditions, including access to and availability of personnel to provide design or construction services; and
  • (vii) District input and recommendations regarding delivery method.