Section 14-2 - Relationship Between the State Construction Department and School Districts

(a) Master Memoranda of Understanding (MOU's) and Project Agreements shall be developed to establish the working relationship between the Department and the district.

  • (i) Master MOUs. The Master MOU defines the duties and responsibilities of the Department and the district for non-capital construction functions, including, but not limited to, major building and facility repair and replacement, facility planning, condition assessments, and annual reporting.
  • (ii) Project Agreements. Project Agreements define the duties and responsibilities of the Department and the district for construction and renovation of school buildings and facilities, including, but not limited to, determination of the most cost effective remedy, land purchase, design, procurement and construction. No work or disbursement of funds shall proceed on projects until a Project Agreement is executed between the Department and the district. Districts shall not expend any appropriated project funds until authorized by the Director.

(b) Departmental Review. The Department shall review school construction projects for compliance with uniform statewide adequacy standards. This review shall be ongoing throughout the planning, budgeting, design, and construction process.

027-14 Wyo. Code R. § 14-2

Adopted, Eff. 11/19/2018.