(a) Each Company shall file on or before May 1st of each year an annual report for the preceding calendar year in the form prescribed by the Commission. All annual reports shall be signed by the officer, manager or agent of the Company under whose direction the annual report is prepared.
(b) Companies and CPCN holders shall preserve the following records for at least three years after the date of entry of the record: - (i) Held service orders.
- (A) The Company shall keep records, by local exchange area, of each instance of a held service order. The record shall indicate the name and address of each applicant for telecommunications service, the date of application, the class of service applied for, whether the held service is for a first line or an additional line, the reason for the delay, the expected date of service and whether a construction agreement was executed.
- (B) The Company shall maintain by local exchange area the total number of held service orders categorized by reason for delay and by dates of application without regard to the length of time the application has been held or the estimated cost of fulfilling the order.
- (ii) Maintenance and operations records. Records of the tests and inspections, necessary for the Company to fulfill the requirements of these Rules, shall be maintained. Corrective maintenance records shall identify the line or facility tested or inspected. The records shall include sufficient detail to show that adequate testing conditions existed and that timely and effective corrective action was undertaken;
- (iii) Customer trouble reports. The Company shall maintain customer trouble reports by local exchange area through which patterns and trends indicating the need for plant improvement may be identified;
- (iv) Record of construction charge estimates. The Company shall maintain a record of each issuance of a construction charge estimate, as set forth in section 7(c) of these Rules. The record shall include the name and address of each applicant for telecommunications service, the date the construction charge estimate was sent to the applicant, the class of service applied for, if the request was for a first line or an additional line, the dollar amount of the estimate, a listing of materials needed and whether the estimate involved a group of applicants.
023-4 Wyo. Code R. § 4-15