020-1 Wyo. Code R. § 1-50

Current through April 27, 2019
Section 1-50 - General Requirements

(a) Implementation of Requirements. Owners and/or operators shall comply with the requirement of this Part for UST systems with field-constructed tanks and airport hydrant systems as follows:

  • (i) For UST systems installed on or before October 13, 2015, the requirements are effective according to the following schedule:

    Requirement Effective Date
    Upgrading UST systems; general operating requirements; and operator training October 13, 2018
    Release detection October 13, 2018
    Release reporting, response, and investigation; closure; financial responsibility and notification (except as provide in paragraph (b) of this Section) October 13, 2015

  • (ii) For UST systems installed after October 13, 2015, the requirements apply at installation.

(b) Not later than October 13, 2018, all owners and/or operators of previously deferred UST systems shall submit a one-time notice of tank system existence to the department using a form developed by the department. Owners and/or operators of UST systems in use as of October 13, 2015, shall demonstrate financial responsibility at the time of submission of the notification form.

(c) Except as provided in Section 51, owners and/or operators shall comply with the requirements of Parts A through E, G, L, and N.

(d) In addition to the codes of practice listed in Section 6, owners and/or operators may use military construction criteria, such as the UFC3-460-01 as referenced in Section 2, when designing, constructing, and installing airport hydrant systems and UST systems with field-constructed tanks.

020-1 Wyo. Code R. § 1-50

Adopted, Eff. 6/29/2018.