020-17 Wyo. Code R. § 17-5

Current through April 27, 2019
Section 17-5 - Program Requirements

(a) Investigation of contamination, design and installation of monitoring and remediation systems, and the operation and maintenance of monitoring and maintenance systems shall be conducted pursuant to the requirements of Chapter 2, Section 8.

(b) All corrective actions shall restore the environment to a condition and quality consistent with the requirements of Chapter 2.

  • (i) In carrying out monitoring and remediation activities under the program the Department has the right to construct and maintain any structure, monitor well, recovery system, or any other reasonable and necessary item associated with taking remediation and monitoring actions.

(c) Any person conducting groundwater monitoring at a facility must report to the Department in accordance with Chapter 2, Section 6(b).

  • (i) The Department shall notify the affected public of all confirmed releases requiring a plan for remediation, and, upon request, provide or make available to the interested public information concerning the nature of the release and the remediation actions planned or taken.

(d) All records created during the development of the remedial activities are required to be maintained by the operator and submitted to the Department in accordance with the requirements of Chapter 2, Section 8.

(e) Construction contractors employed to conduct construction activities at an eligible facility must adhere to the requirements of this Chapter and the Solid Waste Rules and Regulations. All such construction contractors must be registered and bonded with the State.

(f) Right of Inspection. Any authorized agent of the Department has the right of entry for the purposes of inspection, assessment or implementation of corrective actions at eligible facilities.

020-17 Wyo. Code R. § 17-5