(a) Plans and specifications with supporting data must be prepared by a professional engineer who is registered in this state, an architect who is registered in this state, or a licensed contractor who holds a license issued by the state contractors' board and shall: - (i) Include the seal or signature of the registered engineer or architect; or
- (ii) Include the signature of the licensed contractor.
(b) The plans must be: - (ii) Contain a north arrow; and
- (iii) Must be accompanied by proper specifications so as to permit a comprehensive public health review of the plans.
(c) One set of plans shall be submitted, and must include: - (i) The surface area of the pool;
- (ii) The volume, turn-over time, flow rate, filter and automatic chemical feed apparatus, filter head loss and pump curve showing design flow;
- (iii) The source of the water used;
- (iv) The means of disposing wastewater according to law;
- (v) Plan and sectional views with all necessary dimensions of the facility;
- (vi) A piping diagram showing all appurtenances including treatment facilities in sufficient detail, as well as pertinent elevation data to permit a hydraulic analysis of the system;
- (vii) Details on all treatment equipment, including:
- (A) The manufacturer, make and model numbers of the pump, filter and automatic chemical feed apparatus,
- (B) Filter head loss; and
- (C) Pump curve showing design flow.
- (viii) Catalog identification;
- (A) If mechanical equipment is specified by the use of a trade name or catalog numbers, individual leaflets, catalogs, equipment specification sheets or other descriptive material must be furnished. This material will be returned to the applicant on his request after the review of the plans.
- (ix) An electrical diagram showing the method of grounding, junction boxes and other pertinent details;
- (x) Detailed plans of bathhouses, equipment rooms, dressing rooms, toilet facilities, showers and other appurtenances;
- (xi) One site plan with a legal description of the pool location; and
- (xii) Any additional data required by the regulatory authority for purposes of clarification, anticipated use or to support any changes in design or scope of the project must be submitted prior to construction.