Wis. Admin. Code Department of Natural Resources NR 333.08

Current through October 28, 2024
Section NR 333.08 - Construction
(1) Construction of a new dam or reconstruction of an existing dam may not begin until the department approves the plans and specifications submitted under s. NR 333.05.
(2) Alterations to any plans or specifications that were approved by the department under s. NR 333.05 which will affect the flood flow capacity or structural integrity of a dam shall be approved by the department before construction or reconstruction of the dam.
(3) All dams shall be constructed or reconstructed under the supervision of a professional engineer registered in the state of Wisconsin. The supervising engineer shall, within 10 days after completing the construction or reconstruction of a dam, submit a statement indicating that the dam was constructed or reconstructed in accordance with the plans and specifications approved by the department under s. NR 333.05.
(4) As-built plans shall be submitted to the department within 30 business days after the completion of construction or reconstruction of a dam.

Wis. Admin. Code Department of Natural Resources NR 333.08

Cr. Register, May, 1985, No. 353, eff. 6-1-85; CR 00-136: am. (3), Register July 2001, No. 547 eff. 8-1-01.