Section NR 507.09 - Leachate head well design and installation

All leachate head wells required under s. NR 504.09(2) (i) shall be located, designed and installed so as to obtain reliable and representative information regarding the leachate head levels within the landfill. Leachate head wells in landfills with a composite liner shall be designed with risers on the sideslopes. Landfills with a clay liner shall use a vertical leachate head well design. All leachate headwells shall be documented in accordance with s. NR 507.14(1) and (5) (a).

Wis. Admin. Code Department of Natural Resources NR 507.09

Cr. Register, June, 1996, No. 486, eff. 7-1-96.