Section NR 500.09 - Construction inspection

The department may require as a condition of a grant of exemption, the approval of a feasibility report, plan of operation, groundwater monitoring plan, closure plan, site investigation report and remedial action options report or a modification to any approval that critical construction steps of a facility, as specified in the approval, be inspected by the department. The applicant shall pay an inspection fee as specified in s. NR 520.04(5).

Wis. Admin. Code Department of Natural Resources NR 500.09

Cr. Register, January, 1988, No. 385, eff. 2-6-88; am., Register, June, 1996, No. 486, eff. 7-1-96.