Wis. Admin. Code Department of Natural Resources NR 734.15

Current through November 25, 2024
Section NR 734.15 - Request for proposal
(1)Upon selection of one or more qualified consultants, the selection committee shall transmit to the consultants the department's project scope of work and a request for a proposal for completing the project.
(2)The selection committee may request proposals from any number of qualified consultants.
(3)The department's proposed project scope of work shall include all of the following:
(a) Consultant reporting requirements.
(b) Consultant data generation requirements.
(c) The requirements for a site safety plan.
(d) A copy of the department's standard contract.
(e) Any other project-specific requirements.
(4)The request for proposal shall specify a date by which the consultant's proposal shall be submitted to the department. If the consultant cannot provide the completed proposal by the time specified, the department may either grant a time extension or deem the consultant non-responsive and remove the consultant from further consideration for the project.
(5)The consultant's proposal shall include all of the following:
(a) A detailed description of the work to be completed.
(b) A list of key personnel expected to work on the project and their qualifications pursuant to ch. NR 712.
(c) A cost breakdown for the work to be performed, by task and assigned personnel.
(d) A list of subcontractors expected to work on the project and their qualifications pursuant to ch. NR 712.
(e) A quality assurance and quality control plan.
(f) A site safety plan.
(g) A proposed schedule for completing each phase of work.

Wis. Admin. Code Department of Natural Resources NR 734.15

Cr. Register, April, 1994, No. 460, eff. 5-1-94; CR 12-023: cr. (5) (g) Register October 2013 No. 694, eff. 11-1-13.