Current through October 28, 2024
Section NR 734.07 - Selection process(1) A list of consultants that, based on an accurate and completed consultant data record form, possess the necessary capabilities for each proposed project shall be provided to the selection committee members.(2) The selection committee shall review the requirements of each project and the qualifications of consultants and select a consultant considered to be appropriate for each project.(3) When selecting a consultant, the selection committee may utilize any of the procedures specified in ss. NR 734.09, 734.11 and 734.13, for projects with projected costs less than $2,500,000.(4) For projects with projected costs greater than $2,500,000, the selection committee shall utilize the procedures in s. NR 734.13.Wis. Admin. Code Department of Natural Resources NR 734.07
Cr. Register, April, 1994, No. 460, eff. 5-1-94.