Wis. Admin. Code Department of Natural Resources NR 708.07

Current through November 25, 2024
Section NR 708.07 - Additional response actions

Unless s. NR 708.09 is applicable, responsible parties shall conduct all necessary additional response actions at the completion of an immediate action including, but not limited to, the actions listed in subs. (1) to (4), either at the direction of the department or where the responsible party has determined that site or facility conditions warrant an additional response action:

(1) Additional immediate action in accordance with this chapter.
(2) Interim action, in accordance with this chapter and, as applicable, ch. NR 724.
(3) A site investigation, in accordance with the requirements of ch. NR 716.
(4) Implementation of a preventive measures plan to minimize or prevent any further hazardous substance discharges.

Wis. Admin. Code Department of Natural Resources NR 708.07

Cr. Register, April, 1994, No. 460, eff. 5-1-94; r. and recr. (intro.), Register, March, 1995, No. 471, eff. 4-1-95.