Note: For example, the facility's records of analyses performed on the waste before the effective date of these rules, or studies conducted on hazardous waste generated from processes similar to that which generated the waste to be managed at the facility, may be included in the data base required to comply with par. (a). The owner or operator of an off-site facility may arrange for the generator of the hazardous waste to supply part of the information required by par. (a), except as otherwise specified in s. NR 668.07(2) and (3). If the generator does not supply the information, and the owner or operator chooses to accept a hazardous waste, the owner or operator is responsible for obtaining the information required to comply with this section.
Note: See s. NR 660.21 for related discussion.
Note: Chapter NR 670 requires that the waste analysis plan be submitted with the feasibility and plan of operation report.
Wis. Admin. Code Department of Natural Resources NR 664.0013