Note: The department recognizes pollution control equipment start-up problems may arise at the commencement of a new discharge. Enforcement discretion may be used in the 90 days following commencement of discharge, in such cases.
Wis. Admin. Code Department of Natural Resources NR 106.117
An interim permit requirement is not necessarily a numerical effluent limitation.
Note: Compliance schedule provisions for TMDL-based limits, technology-based limits, and phosphorus limits may differ from the requirements of this section. These provisions may be found in ss. NR 212.75(5), 205.14, and 217.17, respectively