Section 69-7-11 - Plans of Correction
11.1. Within ten working days after receipt of the inspection report, the program sponsor or administrator shall submit to the secretary for approval a written plan to correct all deficiencies that are in violation of this rule, unless a variance is requested by the opioid treatment program and granted by the secretary. The plan of correction shall specify:
11.1.a. Any action taken or procedures proposed to correct the deficiencies and prevent their reoccurrence;
11.1.b. The date of completion of each action taken or to be taken; and
11.1.c. The signature of the head of the governing body or his or her designee.
11.2. The proposed plan of correction shall be approved, modified or rejected by the secretary in writing. The opioid treatment program may make modifications to the plan at a later date in conjunction with the secretary.
11.3. The secretary shall state the reasons for rejection or modification of any plan of correction.
11.4. The program sponsor or administrator shall submit a revised plan of correction to the secretary within ten working days of receipt of a rejection by the secretary.
11.5. The opioid treatment program shall immediately correct a violation that severely risks the health or safety of a patient or other persons.
11.6. The secretary shall determine if satisfactory corrections have been made and advise the program sponsor of any compliance or continued deficiencies in writing.
11.7. The secretary may provide consultation to the applicant or licensee in obtaining compliance with this rule.