Current through Register Vol. XLI, No. 50, December 13, 2024
Section 65-03-10 - Time periods10.1. In each instance in this rule where a time period is stated, the period is intended to be a maximum period. In the event a given task is completed sooner than the stated period by the Authority, the board, a hospital or an interested party, then the next time period, if any, shall begin to elapse upon the actual completion date.10.2. Calculation of time periods - Whenever in this rule the date by which some action is directed to be taken or accomplished would fall on a Saturday, Sunday or a state holiday, then the time for taking or accomplishing the action shall be extended to the next day which is not a Saturday, Sunday or a state holiday.W. Va. Code R. § 65-03-10