Current through Register Vol. XLI, No. 50, December 13, 2024
Section 60-11-8 - Penalties8.1. If the owner of the solar or wind generation facility fails to submit a decommissioning bond acceptable to the department or the properly executed and legally binding decommissioning agreement within the timeframe required by these rules, the department shall provide notice to the facility owner. If, after 30 days, the owner has not submitted a decommissioning bond or such agreement, the department may assess an administrative penalty of not more than $10,000.00 for the first day of violation and may assess an additional administrative penalty of not more than $500.00 for each day the failure to submit the bond continues.8.2. The owner of the solar or wind generation facility may appeal a penalty assessment to the Environmental Quality Board within 30 after receipt of written notice of the penalty.