Current through Register Vol. XLI, No. 50, December 13, 2024
Section 53-4-9 - Criterion for Approval of Proposed Project's Application9.1. Not more than ninety (90) days after the public hearing is completed, the Authority shall issue its final decision on the project's application. In reaching a decision, the Authority shall consider whether:a. The proposed project evidences fewer undesirable environmental, economic and cultural consequences in the specific proposed location of the project and the proposed location of its highways, rail lines, electric transmission lines or natural gas pipelines route than alternative specific locations; andb. Whether the proposed project would have a positive and beneficial effect upon the economy and employment.