Section 45-41-21 - Submission of CAIR Permit Applications
21.1. Duty to apply. -- The CAIR designated representative of any CAIR SO2 source required to have a Title V operating permit will submit to the Secretary a complete CAIR permit application under section 22 for the source covering each CAIR SO2 unit at the source at least 18 months (or such lesser time provided by the Secretary) before the later of January 1, 2010 or the date on which the CAIR SO2 unit commences commercial operation.
21.2. Duty to reapply. -- For a CAIR SO2 source required to have a Title V operating permit, the CAIR designated representative will submit a complete CAIR permit application under section 22 for the source covering each CAIR SO2 unit at the source to renew the CAIR permit in accordance with 45CSR30.