Current through Register Vol. XLI, No. 50, December 13, 2024
Section 45-19-24 - Conflict with Other Permitting Rules24.1. For sources required to obtain a permit under this rule, the provisions of 45CSR13 and 45CSR14 requiring a permit do not apply, so that only a single preconstruction permit is required; provided however, that: 24.1a. The base permit application fee of $1,000 pursuant to 45CSR22, subdivision 3.4.a shall apply to such sources in addition to other applicable fees; and24.1b. Any permit issued under this rule includes conditions that ensure compliance with the provisions of 45CSR13 and 45CSR19 to the extent applicable to any regulated NSR pollutant not otherwise covered under this rule.24.2. For sources that may be subject to 45CSR13, 45CSR14 and/or 45CSR19, the more stringent provisions of each applicable rule shall apply.W. Va. Code R. § 45-19-24