W. Va. Code R. § 33-11-13

Current through Register Vol. XLI, No. 50, December 13, 2024
Section 33-11-13 - Requirements of a Grant Recipient
13.1. All CED recycling grants are for the twelve-month period beginning the first day of October and ending the last day of September of the following year.
13.2. Grant funds will be disbursed at the time a completed grant agreement and all required documents necessary to initiate the grant are received by the department.
13.3. The grantee shall retain and make available upon request by the department, for a period of five years, all financial records, supporting documents, statistical records, and all other records and data as they relate to the application, acceptance and use of the grant.
13.4. The grantee shall deposit the grant immediately upon receipt in a separate account.
13.5. If, through any cause, the grantee fails to fulfill in a timely and proper manner the obligations imposed in the grant agreement or violates any provision of this rule, the department may terminate the grant and the grantee shall immediately return the grant, in its entirety, to the department.
13.6. The grantee shall comply with all federal, state, and local laws, codes, ordinances, rules and regulations.
13.7. The grantee shall solicit sealed bids, by public notice as a Class II legal advertisement in compliance with the provisions of West Virginia Code § 59-3-2, for all purchases that have an estimated cost of five thousand dollars or more. Any attempt to segregate the purchase into sections to circumvent the bidding requirement shall be cause for termination of the grant.
13.8. The grantee shall reimburse the department any amount of the grant used for unauthorized expenditures. Authorized expenditures are those outlined in the budget of the approved application and that have sufficient supporting documentation.
13.9. The grantee shall return any unexpended grant funds remaining at the end of the grant period to the department. If the grantee expends any grant funds after the grant period specified on the grant agreement, those expenditures shall be considered unauthorized.
13.10 The grantee shall submit a final report to the department within 30 days following the last day of the grant period. The report shall contain:
13.10.1. A complete accounting of the grant expended during the period;
13.10.2. Documentation supporting all grant expenditures, including without limitation, invoices, checks, titles and purchase orders;
13.10.3. All bank statements of the grant account;
13.10.4. All bidding information for expenditures costing $5,000 or greater, including copies of the legal ads, bids received, and authorization to purchase;
13.10.5. An evaluation of the total operating costs and community support for the project;
13.10.6. An evaluation of successes and failures encountered in implementing the original application's work tasks;
13.10.7. Program information as described in section 5.4 of this rule; and
13.10.8. An analysis of the project including: the estimated cost per ton to recycle that volume and the estimated revenue per ton of recycled material.
13.11. The department shall return an incomplete report to the grantee for completion. A grantee shall resubmit a completed report within thirty days of notification that the report is incomplete.

W. Va. Code R. § 33-11-13