WVMR(ARMY) 415-10
SOURCES OF TRAINING SITE FUNDS (FEDERAL)
TRAINING SITE CONTRACT (O & M, ARNG)
Utilities
Services and Operating Supplies
Security Guards
maintenqnce personnel
Minor Repairs, Maintenance and Alterations
Hand Tools & Other Equipment
REIMBURSABLE ORDERS (USAR, ACTIVE SERVICES - Based on Attendance)
Applied to Contract Type Items
(Same Areas as Above)
MINOR CONSTRUCTION (O & M, ARNG)
Projects up to $15,000
MCARNG (MINOR AND MAJOR CONSTRUCTION)
Projects up to $175,000 (Minor)
Projects $175,000 and Above (Major)
ENGINEER TNG MATERIALS
Annually Allowed:
CBT ENGR BN:$4,600
Constr Spt Equip Co: $1,500
Engineer Det (Utilities) $ 600
(Not to be used for projects on the Construction Plan)
O & M ARNG APPROPRIATIONS Services & Supply Accounts Technician (1)
PROJECT DEVELOPMENT SEQUENCE | ||||||
(1) *PR0P0NENT | (2)**PRINCIPAL | (3) FACILITIES | (4) INSTALLATION | (5) DEP CMDR/TAG | (6) EXECUTION | |
(Facilities Managers) | STAFF | MANAGEMENT OFFICER | FACILITIES PLANNING BOARD | |||
MCARNG (Major & Minor) | Develop Requirements | Verify Requirements | Add Engineering $ Environmental Supporting Data; Develop Consolidated List in Tent? | Refine/Revise/ Prioritize Project List itive Priority | Approval of List | Facilities Mgt Officer Prepares Package for NGB |
0&M Minor Const | Develop Requirements | Verify Requirements | Refine Cost Estimate; Consolidate List in Tentative Priority | Refine/Revise/ Prioritize Project List | Approval of List | Facilities Mgt Officer Prepares Project Sketch/ Design Bill of Materials for Work Execution by FE Team, R&U Det or Engineer Troops |
Maintenance & Repair | Develop Requirements | Verity Requirements | Refine Cost Estimate; Consolidate List in Tentative Priority | Refine/Revise/ Prioritize Project List | Approval of List | Facilities Mgt Officer Prepares Project Sketch/ Design S Bill of Materials for Wort Execution by FE Team, R&U Det or Engineer Troops |
NOTES: *Obtain input from commanders using the facilities. Commanders* input will be submitted as a brief fact sheet that describes the purpose of the project, location and benefits to be gained, if approved.
**Responsible to obtain technical staff concurrence, if required, e.g., safety; C&E APPENDIX B
PROJECT SUBMISSION DEADLINES | |||
PROGRAM | FACILITIES MGT OFFICER IFPB | IFPB | TAG |
MCARNG | |||
Major | 1 April 1 May | 1 June | 1 July |
Minor | 1 November 1 December | 1 January | 1 February |
Minor Constr | |||
O&M, ARNG | 1 April 1 May | 1 June | 1 July |
Maintenance § | |||
Repair | 1 April 1 May | 1 June | 1 July |
*DETAILED REQUIREMENT STATEMENT
1. GENERAL. Include project title, location, and description of the requirement.
2. DATA ON ACCOMMODATIONS NOW IN USE. Self explanatory.
3. ANALYSIS OF DEFICIENCY. Self explanatory.
4. ANALYSIS OF ALTERNATE FACILITIES AND LOCATIONS. Self explanatory.
*NOTE: Refer to Fig D-6, NGR 41S-5, 27 Feb 81 for example.
MINOR CONST (0&MS ARNG), MAINTENANCE 5 REPAIR
MINOR CONST (O&MS ARNG), MAINTENANCE 5 REPAIR | WVMK(.AKMYJ 415-; DATE ISSUED | |||||
RIORITY | LOCATION | LABOR FORCE | EST COST | PROJECT DESCRIPTION | CONSTR YEAR | REMARKS (INCL ARTEP TASK #) |
W. Va. Code R. agency 141, tit. 141, ser. 141-45, app A