Section 51-51-0903 - Section R903-Weather protection

R903.4.1 Secondary (emergency overflow) drains or scuppers. Where roof drains are required, secondary emergency overflow drains or scuppers shall be provided where the roof perimeter construction extends above the roof in such a manner that water will be entrapped if the primary drains allow buildup for any reason. Overflow drains having the same size as the roof drains shall be installed with the inlet flow line located 2 inches (51 mm) above the low point of the roof, or overflow scuppers having three times the size of the roof drains and having a minimum opening height of 4 inches (102 mm) shall be installed in the adjacent parapet walls with the inlet flow located 2 inches (51 mm) above the low point of the roof served. The installation and sizing of overflow drains, leaders and conductors shall comply with Sections 1101 and 1103 of the state plumbing code. Overflow drains shall discharge to an approved location.

Wash. Admin. Code § 51-51-0903

Amended by WSR 16-03-025, Filed 1/11/2016, effective 7/1/2016

Statutory Authority: RCW 19.27.031 and chapters 19.27 and 34.05 RCW. 13-04-068, § 51-51-0903, filed 2/1/13, effective 7/1/13. Statutory Authority: RCW 19.27.031 and 19.27.074. 10-03-098, § 51-51-0903, filed 1/20/10, effective 7/1/10.