At least ninety days prior to start of construction as defined in WAC 463-68-040, a certificate holder shall provide the plans and specifications required by the site certification agreement to the council for approval.
Wash. Admin. Code § 463-68-050
Statutory Authority: RCW 80.50.040(1) and (12). 04-21-013, § 463-68-050, filed 10/11/04, effective 11/11/04.