Wash. Admin. Code § 296-900-15015

Current through Register Vol. 24-17, September 1, 2024
Section 296-900-15015 - Progress reports
(1) You must submit written progress reports on corrections when required in the citation and notice (C&N) or corrective notice of redetermination (CNR), and briefly explain the:
(a) Status of each violation.
(b) Action taken to correct each violation.
(c) Date each action has or will be taken.

What to expect from WISHA:

(2) WISHA will state in the C&N or CNR if progress reports are required, including:
(a) Items that require progress reports.
(b) Date when an initial progress report must be submitted. The initial progress report is due no sooner than thirty calendar days after you submit a correction action plan.
(c) Whether additional progress reports are required, and the dates by which they must be submitted.

Wash. Admin. Code § 296-900-15015

Amended by WSR 17-18-075, Filed 9/5/2017, effective 10/6/2017

Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050, 49.17.060. 06-06-020, § 296-900-15015, filed 2/21/06, effective 6/1/06.