Wash. Admin. Code § 296-400A-015

Current through Register Vol. 24-23, December 1, 2024
Section 296-400A-015 - What requirements must be met if a plumbing contractor changes its business structure, name, address, or designated plumber?
(1) If a plumbing contractor changes its business structure (for example, from a partnership to a corporation or if the partners in a partnership change or change in the designated plumber that changes the scope of work that can be performed), the plumbing contractor must:
(a) Apply for a new plumbing license as required in WAC 296-400A-011; and
(b) Pay the plumbing license fee shown in WAC 296-400A-045.
(2) If a plumbing contractor changes its designated plumber without a change in the scope of work that can be performed, the plumbing contractor must:
(a) Submit a new designated plumber form as required in WAC 296-400A-011.
(b) Pay the change designated plumber fee shown in WAC 296-400A-045.
(3) Failure to relicense after a change in business structure may invalidate the plumbing contractor's license. See RCW 18.106.410.
(4) If a licensed plumbing contractor changes its name, it must:
(a) Notify the department, in writing, of the change; and
(b) Pay the relicensing fee shown in WAC 296-400A-045; and
(c) Submit to the department a name change rider or a new bond in the new name and a certificate of insurance in the new name.
(5) If a licensed plumbing contractor changes its address, it must notify the department in writing.

Wash. Admin. Code § 296-400A-015

Adopted by WSR 21-13-041, Filed 6/10/2021, effective 7/1/2021