The department will normally act upon a permit application within sixty days of receipt of a complete permit application, except in the case of an historic archaeological resource where the applicant is not the holder of the right of first refusal. Such applications shall be subject to the provisions of WAC 25-48-085. The department may issue a permit for a specified period of time appropriate to the work to be conducted upon determining that:
The director, in his or her discretion, may negotiate the terms of such contracts.
Wash. Admin. Code § 25-48-090
Statutory Authority: RCW 27.34.220, 27.53.140, 43.21C.120. 06-06-001, § 25-48-090, filed 2/15/06, effective 3/18/06. Statutory Authority: RCW 27.34.220 and 27.44.020. 90-01-091, § 25-48-090, filed 12/19/89, effective 1/19/90. Statutory Authority: RCW 27.53.030, 27.53.060, 27.53.080 and 1988 c 124 §§ 1, 3, 5, 6 and 7. 88-23-004 (Order 88-06), § 25-48-090, filed 11/4/88. Statutory Authority: RCW 27.34.220 and 27.44.020. 86-13-001 (Order 11), § 25-48-090, filed 6/5/86.