Wash. Admin. Code § 194-40-050

Current through Register Vol. 24-23, December 1, 2024
Section 194-40-050 - Submission of clean energy implementation plan
(1) Each utility must submit by January 1, 2022, and every four years thereafter, a CEIP for resources to be acquired and other actions to be undertaken during the next interim performance period or GHG neutral compliance period to comply with the GHG neutral standard and the 100% electricity clean standard. The CEIP must be submitted using a form provided by commerce.
(2) Each utility must submit with its CEIP a summary of the public input process conducted in compliance with WAC 194-40-220 and a description of how public comments were reflected in the specific actions under WAC 194-40-200(4), including the development of one or more indicators and other elements of the CEIP and the utility's supporting integrated resource plan or resource plans, as applicable.

Wash. Admin. Code § 194-40-050

Adopted by WSR 21-02-039, Filed 12/29/2020, effective 1/29/2021